e|agenda.NET
Sarasota County Schools
November 6, 2018 Special Board Meeting
Agenda Item #39


Title
APPROVAL OF AMENDMENT #8 TO ARCHITECT'S CONTRACT FOR THE VENICE MIDDLE SCHOOL HVAC RENOVATION AND BUILDING UPGRADES

Description
The scope of work for this amendment is to provide additional electrical design services for the redesign of the operational sequencing of the existing kitchen hoods. The total amount for these changes shall not exceed $3,270.00. These funds are available through the project 5573 budget.

Recommendation
That Amendment #8 to the Agreement dated March 1, 2016, with Harvard Jolly, Inc., for the Venice Middle School HVAC Renovation and Building Upgrades be approved as presented.

Contact
MAULTSBY & SMITH

Financial Impact
$3,270.00


Attachment:  Amendment#8 _VMS.pdf